............ Infrastructure & Civil Work Projects ......

Our Completed Projects

A brief overview of the projects that we have completed 
as a subcontractor

Owner

Project title: Construction of infrastructure at Al Fursan area 65

Scope of work: Simple Infrastructre

We worked as  a Sub Contractor With Binjarallah Contracting Co. 
For 42 Months Started 2018/01/17 To 2021/06/16 At a cost of 162398834.88 SAR

Owner

Project title: Construction of Civil Work in Internal Maitanance At area SA-3B

Scope of work: Road Work

We worked as  a Sub Contractor With Kentz Saudi Arabia.
For 48 Months Started 2016/07/01 To2020/07/01 With a cost of 36493253 SAR

Owner

Project title: Infrastructure Of Khab Al radhwan 48 Qassim Area

Scope of work: Simple Infrastructre

We worked as a Sub Contractor With Ansab Contracting Co. 
For 6 Months Started 2019/12/01 To 2020/06/06 With a cost of 162398834.88 SAR

Owner

Project title: Construction Of Alkharj Road project stage 3

Scope of work: Road Work

We worked as a Sub Contractor With Alshallawi Contracting Co.
For 10 Months Started 2019/08/01 T o2020/05/31 , With a cost of 36493253 SAR

Owner

Project title: Construction of Civil Work in King Faisal Air College Majmaah

Scope of work: Road Work

We worked as  a  Sub Contractor With SAJCO .
For 11 Months Started 2020/10/01 To 2021/08/31 With a cost of 9188861 SAR

Owner

Project title: Construction Of Alkharj Road project stage 3

Scope of work: Road Work

We worked as  a Sub Contractor With Al Rashid Technichal And Energy Co.
For 6 Months Started 2019/05/15 T 2021/10/01 With a cost of 3072500 SAR

Owner

Project title: Construction of infrastructure at Harma 1308 Majmaah

Scope of work: Simple Infrastructre

We worked as  a  Sub Contractor With Beijing Emirates Co.
For 3 Months Started 2021/07/01 To 2021/10/01 With a cost of 4484000 SAR

Owner

Project title: Construction of infrastructure at NEOM Gulf

Scope of work: Road Work

We worked as  a  Sub Contractor With SAJCO.
For 13 Months Started 2021/11/21 T 2022/12/31. With a cost of 16696900 SAR

Owner

Project title: Construction of infrastructure at NEOM Gulf

Scope of work: Road Work

We worked as  a  Sub Contractor With SAJCO.
For 13 Months Started 2021/11/21 T 2022/12/31. With a cost of 8300000 SAR

Owner

Project title: Extension of pipelines At Al Mazalaj & Abu Jafan Khurais- Hawtah

Scope of work: Excavation & Embankment

We worked as  a  Sub Contractor With ARKAD Co. 
For 6 Months Started 2018/01/01 To2018/06/30 . With a cost of 3,208,000.00 SAR

Owner

Project title: Extension of pipelines At Al Mazalaj & Abu Jafan Khurais- Hawtah

Scope of work: Excavation & Embankment

We worked as  a  Sub Contractor With ARKAD Co.
For 12 Months Started 2021/01/01 To2021/12/31 With a cost of 3604432 SAR

Owner

Project title: Extension of pipelines At NYYM

Scope of work: Excavation & Embankment

We worked as  a  Sub Contractor With Gulf Consolidated Company.
For 8 Months Started 2021/05/01 To2021/12/31 With a cost of 3599100 SAR

Owner

Project title: Prepaation of Al Jafura Site Al Ahsa

Scope of work: Road Work

We worked as  a  Sub Contractor With Al Yamama Contracting Co.
For 17 Months Started 2022/11/21 To 2023/05/13 , With a cost of 3795000 SAR

Owner

Project title: Infrastructure & Tropography In King Salman Park Riyadh

Scope of work: Road Work

We worked as  a  Sub Contractor With Haif Contracting Co.
For 18 Months Started 2022/03/23 To 2023/09/22 , With a cost of 15000000 SAR

Owner

Project title: Infrastructure & Tropography In King Salman Park Riyadh

Scope of work: Road Work

We worked as  a  Sub Contractor With Al Yamama Contracting Co.
For 12 Months Started 2022/11/17 To 2023/11/16 , With a cost of 10062500 SAR

Owner

Project title: Construction of Civil Work in Internal Maitanance At area SA-3B

Scope of work: Road Work

We worked as  a  Sub Contractor With Kentz Saudi Arabia co.
For 6 Months Started 2022/12/01 To 2023/05/31 , With a cost of 7261135 SAR

Our Current Projects

A brief overview of the Current projects 

Owner

Project title: Remaining work of Completion of some roads projects , Haiel region - Group 14

Scope of work: Road and Bridgs Work

As  a  Main contractor in Ministry of Transport project
For 36 Months, With a cost of 69195556.35 SAR

Owner

Project title: Remaining work of Completion of some roads projects , Qasseem region - Group 3

Scope of work: Road and Bridgs Work

As  a  Main contractor in Ministry of Transport project
For 24 Months, With a cost of 75038992.7 SAR

Owner

Project title: Construction of steel fence , Riyadh region No. (4)

Scope of work: steel fence and electric work

As  a  Main contractor in Ministry of Defence
For 8 Months, With a cost of 2173500 SAR

Owner

Project title: Construction of steel fence and concrete fenceat Alshifaa and Ramah , Riyadh region

Scope of work: steel fence , concrete fence , fiber optic , camera and electric workc work

As  a  Main contractor in Ministry of Defence project
For 18 Months, With a cost of 12452540.04 SAR